How a Brownfield Expansion Became a Catalyst for Better Asset Management

Five Lessons from an Asset Maintenance Build That Delivered Benefits Beyond the Project

Brownfield expansion projects are often treated as delivery exercises focused on capacity, infrastructure and production uplift, but they can also be powerful opportunities to strengthen the operating model that will sustain the asset long after commissioning.

During a recent brownfield expansion project, EnterpriseIS supported the development of an asset maintenance build for a new processing facility that operated largely independently from the existing plants by facilitating workshops, translating technical and operational knowledge into maintainable strategies, and aligning the workstream with the client’s asset management and maintenance system requirements.

The organisation already had established systems, operational experience and maintenance practices. At the same time, the expansion was sufficiently separate from the existing plant to allow the asset maintenance build to be developed as a focused and structured workstream.

What began as an asset maintenance build for a new facility ultimately became a structured improvement opportunity, establishing a higher benchmark for maintenance strategy development, planning discipline, system alignment and repeatable asset management practices across the organisation.

The project reinforced five important lessons that organisations can apply when preparing new assets, facilities or major expansion projects for operation.

Lesson 1: Start Before Commissioning Is Complete

One of the most significant lessons was the value of timing.

The asset maintenance build was completed in the months leading up to commissioning. This allowed the project team to access key personnel while asset knowledge was still current, project decisions were still fresh and key documents were still readily available.

Too often, asset management activities commence after knowledge has already started dispersing throughout the organisation. Project personnel move to new roles, operational stakeholders become focused on start-up issues and supporting documentation becomes harder to locate or validate.

By engaging early, important project knowledge could be converted into operational capability before it was lost. This improved the quality of the asset information, reduced the need for later assumptions and created a stronger foundation for maintenance planning.

Lesson 2: Bring the Right Stakeholders Together

Asset management outcomes improve when multiple perspectives are considered.

Workshops involving project personnel, operational stakeholders and maintenance specialists created an environment where maintenance requirements could be reviewed collectively. The inclusion of personnel from existing operations was particularly valuable because it brought real operating experience into the development of maintenance plans and preventative maintenance inspections (PMIs).

Rather than relying solely on manufacturer recommendations, the project team tested maintenance requirements against how the equipment would actually be operated, accessed, maintained and supported, ensuring the resulting strategies were practical, risk-based and aligned with site realities.

The process also created a useful knowledge exchange. Existing operations informed the new facility, while the new asset maintenance build provided an opportunity to challenge and improve existing maintenance practices.

Lesson 3: Use Criticality and FMECA Reviews to Capture Operational Knowledge

A maintenance strategy is strongest when it reflects both technical requirements and operational experience.

Criticality and FMECA workshops provided an effective mechanism for incorporating site knowledge into maintenance planning. These discussions helped identify operational considerations that may not always be evident within equipment documentation alone and ensured maintenance strategies were aligned with operational risk and reliability objectives.

For EnterpriseIS, this was a critical translation point: converting criticality outcomes, failure mode insights and operational experience into practical maintenance tasks that could be planned, scheduled and executed by the maintenance team.

The result was a stronger maintenance framework that connected asset criticality, risk, operational experience and field execution.

Lesson 4: Align Maintenance Systems Early

Asset structures and maintenance systems need to work together.

Early engagement with maintenance system stakeholders enabled the asset hierarchy and SAP structures to align with established organisational standards. This reduced rework, improved consistency and supported a smoother transition from project delivery into operational execution.

This step is often overlooked, but it has a significant impact on the long-term usability of maintenance systems and asset information. A maintenance strategy may be technically sound, but if the master data structure is inconsistent or difficult to use, the value of the strategy can be reduced during execution.

Aligning system structures early helped ensure that maintenance plans, PMIs and asset information were not simply prepared as project documents, but embedded into the maintenance system in a format that supported future planning, scheduling, governance and continuous improvement.

Lesson 5: Look Beyond the Project Boundary

Perhaps the most valuable lesson was that the improvement opportunity extended well beyond the new facility itself.

Because the workshops included personnel from existing operations, the project became an opportunity to review and challenge maintenance practices across a much broader asset base. Similar equipment operating elsewhere in the organisation could benefit from improved maintenance strategies, PMIs and planning approaches developed during the project.

This created a compounding benefit: improvements developed for one facility could be replicated across similar assets, improving maintenance efficiency, reducing planning variability and supporting more consistent preventative maintenance across multiple operations.

The broader outcome was not simply a better asset maintenance build for the expansion. It was the creation of a new benchmark for asset management processes and systems that could influence maintenance practices across the wider operation.

Conclusion

While asset maintenance builds are often viewed as project deliverables, the most successful ones become opportunities for organisational improvement.

By engaging stakeholders early, capturing operational knowledge, aligning maintenance systems and translating strategy into executable maintenance plans and PMIs, organisations can reduce operational risk, improve readiness, lift maintenance maturity and create value that extends well beyond the initial capital project.

In this case, the brownfield expansion became more than an asset maintenance build: it provided a practical operating benchmark that can continue to support safer, more reliable and more disciplined asset management performance across the wider business.

Contact Us

If your organisation is planning a brownfield expansion, major shutdown, new facility or asset transition, EnterpriseIS can help turn the maintenance build into a broader asset management improvement opportunity. Contact us to discuss how a structured, risk-based approach can support your next project.